| Hurricane
Irene Aftermath |
|
|
|
|
BRIDGING
THE GAPS: High seas from Katia suspended road work Thursday night
...WITH SLIDE SHOW
By ANNE C.
BOWERS
“We would
be a lot
further along if it wasn’t for Mother Nature,” offered DOT project
inspector Milton Joyner.
Hurricanes continue to be problematic for Highway 12, which was severed
in multiple areas by Hurricane Irene on Aug. 27. Yesterday,
Hurricane Katia stayed well offshore of Hatteras Island but pushed some
mighty rollers to the area, which aggravated the rebuilding efforts to
this vital road.
During the low tide that occurred around midnight on Wednesday night,
Waff Contracting from Edenton, N.C., reset the existing protective
sandbags to provide a more even line of defense to the Mirlo Beach
area, which is located in northernmost part of Rodanthe.
Equipment problems hampered efforts to make new sandbags to secure the
area where Mirlo Inlet came through.
During the same time, drivers worked late Wednesday night hauling
enough sand about five miles north to the southernmost breach on Pea
Island. Barnhill Contracting said its crews succeeded in
connecting the sections of roads in that area around midnight.
Earlier in the week, the northernmost breach on Pea Island was linked
up with the remaining highway. Even though the Mirlo Beach
area
continues to be challenged by the persistent ocean, three areas have
been filled which leaves the major task of filling the New New Inlet on
Pea Island near the ranger station.
Rebuilding efforts at Mirlo Beach suffered a small setback at the first
high tide on Thursday, which happened just before dawn. Some
of
the repairs were lost, which temporarily made the single lane sand road
impassable for a short time but crews got it repaired and then spent
the day shoring up just this area.
Conditions got rough Thursday afternoon when Hurricane Katia came
within a couple hundred miles of the coast. Fueled by a high
tide
at about 5:30 p.m. and a lunar tide, the area at Mirlo Beach was yet
again under fire, and nature was undoing what man had just done.
Waves were breaking hard over the sandbags and washing over the single
lane sand road, displacing the wooden walk mats again. Water
poured through the area and made its way towards the sound.
Around 3 p.m., travel across this area was abandoned, and crews pulled
back where the oceanfront houses are located to regroup and
re-strategize.
The heavy equipment started working again after a short break to defend
the area south of the large Mirlo Beach sign. At least 60
more
truckloads of sand were piled in this one area to protect the area
south of where the sandbag barricade stopped.
The drivers who were lined up on a side road waiting for their turn to
dump sand were parked in ocean overwash that poured in between the line
of oceanfront houses. Pilings, boards, and other debris had
to be
removed by hand before the trucks could move forward to the new battle
line.
Workers were anticipating a night off because there wasn’t much that
could be done until the ocean backed off.
Work continues at the New New Inlet on Pea Island as crews ready the
area for the temporary bridge. Large cranes can be seen
working
on the area.
This growing inlet suffered more erosion at the hand of Hurricane
Katia. On Thursday afternoon, the ocean was visibly racing
through the inlet towards the sound. Water was also pushing
outside of the inlet into breached areas but the crude sand road seemed
to be unaffected.
Since Irene, the seas have not cooperated with the rebuilding efforts
for Highway 12. Strong northeast winds filled in shortly
following Irene’s exit and lasted for three days. Then came
the
big swell from Hurricane Katia, coupled with an approaching lunar tide.
Locals are now following the movements of Tropical Storm Maria, which
has been difficult for forecasters to predict but feel that it could
come close to the East Coast.
There are a lot of people, not just on Hatteras Island, who could use a
break from the weather right now.
(The
photos in the slide show were taken at Mirlo Inlet in northern Rodanthe
and at New New Inlet five miles north on Pea Island. The
cranes
and other equipment across the inlet are working on a temporary bridge.)
CLICK HERE TO VIEW SLIDE SHOW
|
  |
|
|